Pembangunan FO Cakung Capai 71 Persen
.
photo Aldi Geri Lumban Tobing - Beritajakarta.id

Cakung Flyover Development Process Has Reached 71 Percent

The Cakung Flyover development process in East Jakarta has reached 71 percent and now has entered the girder lifting stage.

The work has touched 71 percent from the initial plan was 66 percent

Jakarta Bina Marga Agency Head Hari Nugroho said work plans and realization had a positive deviation of five percent. The girder lifting was mainly on the west side of the East Flood Canal (KBT) and flyover girders that cross the railway tracks.

"The work has touched 71 percent from the initial plan was 66 percent. So there is a positive deviation of five percent," he said, Wednesday (9/9).

Illegal Parking Income in Cakung Flyover Reaches Rp 18 M

He expressed around 84 girders would be installed and currently it had reached 72 girders as of September 7. This flyover was built to parse traffic jam caused by railway crossings and minimize accidents.

"That railway crossings will be closed down. So, drivers will be directed through the Cakung Flyover. It is targeted to be complete by the end of this year," he hoped.

Linked News
Popular News indeks
  1. Monas Bus Stop Officially Serves Route 14A Monas - JIS

    access_time30-09-2024 remove_red_eye604 personAldi Geri Lumban Tobing
  2. Jakarta Launches Wolbachia Method as Dengue Fever Handling Program in Kembangan

    access_time04-10-2024 remove_red_eye592 personTP Moan Simanjuntak
  3. Supporting Peparnas XVII in Solo, Transjakarta Sends 10 Low Entry Bus Units

    access_time02-10-2024 remove_red_eye512 personAldi Geri Lumban Tobing
  4. Repair of Sheet Piles on Jalan Pedurenan Masjid IV Completed

    access_time30-09-2024 remove_red_eye506 personTiyo Surya Sakti
  5. Jakarta Entrepreneur Participates in Premiere Classe Exhibition in Paris

    access_time29-09-2024 remove_red_eye475 personAnita Karyati