Cakung Flyover Development Process Has Reached 71 Percent

The Cakung Flyover development process in East Jakarta has reached 71 percent and now has entered the girder lifting stage.

The work has touched 71 percent from the initial plan was 66 percent

Jakarta Bina Marga Agency Head Hari Nugroho said work plans and realization had a positive deviation of five percent. The girder lifting was mainly on the west side of the East Flood Canal (KBT) and flyover girders that cross the railway tracks.

"The work has touched 71 percent from the initial plan was 66 percent. So there is a positive deviation of five percent," he said, Wednesday (9/9).

Illegal Parking Income in Cakung Flyover Reaches Rp 18 M

He expressed around 84 girders would be installed and currently it had reached 72 girders as of September 7. This flyover was built to parse traffic jam caused by railway crossings and minimize accidents.

"That railway crossings will be closed down. So, drivers will be directed through the Cakung Flyover. It is targeted to be complete by the end of this year," he hoped.

Linked News
Popular News indeks
  1. Jakarta Removes Gibran’s Portraits Across All Government Offices

    access_time16-11-2026 remove_red_eye1109 personFakhrizal Fakhri
  2. Transjakarta Offers Free Rides for Jakarta Vertical Run 2026 Participants

    access_time14-11-2026 remove_red_eye704 personAldi Geri Lumban Tobing
  3. Governor Approves Removal of Seven Unauthorized Houses on Dispora Land

    access_time13-11-2026 remove_red_eye672 personFakhrizal Fakhri
  4. Pramono Outlines Measures to Address Five Issues in Kramat Jati

    access_time13-11-2026 remove_red_eye648 personFakhrizal Fakhri
  5. Jakarta Esports 2026 Draws Enthusiastic Crowds at M Bloc Space

    access_time13-11-2026 remove_red_eye633 personTiyo Surya Sakti